Construction progress as of October 15, 2024.

Autumn is gaining momentum, and construction of the Oxford residential complex is proceeding according to plan. Your new home is being actively built – we invite you to familiarize yourself with the construction progress as of October 15, 2024

Building A1

Completed:

  • Elevator cladding;
  • Painting walls in common areas (MZK);
  • Laying tiles in MZK on all floors;
  • Installation of entrance doors;
  • Electrical wiring in apartments (radiators, individual heating);
  • Installation of external engineering networks (rain and domestic sewage);
  • Insulation and installation of the roof.

In progress:

  • Installation of gas risers;
  • Landscaping and landscaping of the territory.

Building A2

Completed:

  • Installation of the 9th floor of TMRoyal wall modules;
  • Installation of interior partitions in apartments.

In progress

  • Installation of heating and water supply systems in apartments;
  • Installation of stone masonry walls and roof.