The construction site of the Oxford residential complex is bustling with activity!
Our team of professionals is working tirelessly to bring your dream of the perfect home closer to reality. As of November 15, 2024, the following work has been completed:
Building A-1
- The interior work in the building is 100% complete.
- Repair work in common areas (MZK) has been completed, as well as the installation of a suspended ceiling, which gives the space a finished and aesthetic look.
- Currently, the elevator in the building and basement is being commissioned.
- Renovation in the spacious and cozy lobby is in its final stages.
- On the roof, work is being completed on decorating the facades of chimneys and ventilation ducts.
- In the bomb shelter, cosmetic repairs are being carried out to create comfortable and safe conditions.
- In parallel, work is underway to improve and green the surrounding area. Soon, residents will be able to enjoy a cozy courtyard with thoughtful recreation areas.



Building A-2
- The installation of interior partitions on all floors has been completed.
- In parallel, work is being carried out on the installation of water supply and heating engineering networks.
- Particular attention has been paid to the roof: work is currently underway to install the roof screed – an important stage that will provide protection from weather conditions.


House A-3
- Installation of wall modules of the TMRoyal House third floor has been completed.